Share this article

MV Distribution for Solar PV & BESS

How to Configure Switchgear, RMUs, and Transformers

A solar farm and a battery storage plant look completely different on the DC side. On the medium-voltage side they are almost the same plant.

Both gather power from dozens of small sources, step it up through a transformer at every block, collect the blocks onto an MV feeder, and hand the energy to the grid at one point of connection. The equipment that does this — compact substations, ring main units, metal-clad switchgear, protection relays — is typically under 10% of project cost, but it causes a disproportionate share of commissioning delays and grid-code rejections.

This guide follows the MV chain from the inverter terminals to the point of connection, explains how to size each element, and shows where an RMU stops being enough.

Key takeaways

  • Size the step-up transformer on the inverter or PCS ACrating, never on the DC array nameplate.
  • Inverter-based sources contribute very little fault current. Protection designed for a synchronous generator will not work here.
  • A BESS is bidirectional. Protection and metering settings copied from a PV plant will fail at the first charge cycle.
  • RMUs are the right answer at block level. Metal-clad switchgear belongs at the collector busbar.
  • SF6-free designs are now a procurement requirement in several markets, not a preference.

1. What the MV side of a PV or BESS plant actually looks like

Whatever the size of the plant, the chain has the same six links:

# Link Typical voltage Equipment
1 Inverter / PCS output 0.4–0.8 kV Inverter, LV panel, aux transformer
2 Step-up 0.4/0.69/0.8 kV → 10/33/35 kV Two-winding transformer, ONAN or dry-type
3 Block isolation 33 kV RMU or compact substation
4 Collection 33 kV MV cable feeder
5 Collector busbar 33 kV Metal-clad switchgear, busbar sections
6 Grid connection 33 → 132/220 kV Main step-up transformer, POC switchgear

 

Two architectures dominate utility-scale projects:

Block architecture. One transformer per inverter block, usually 2–5 MW, mounted on a skid together with an RMU and an LV panel. This is the standard for utility-scale PV because it keeps DC cabling short and lets you commission block by block.

Shared transformer architecture. Several string inverters feed one larger transformer. Common in commercial and industrial rooftops and in smaller BESS, where the number of MV terminations has to stay low.

The important structural point for BESS: an AC-coupled storage system connects to the same collector as the PV arrays. A hybrid plant therefore has one MV system serving two generation profiles, and the switchgear has to be rated for the combined current while the protection has to handle reverse flow.

Single-line diagram of a 100 MW PV and BESS plant medium-voltage collection system, showing 33 kV feeders, transformers, RMUs, and grid connection point.

2. Sizing: from inverter output to transformer kVA

Transformer sizing for renewables is simpler than for a load substation, but it is done wrong often enough to be worth stating as rules.

A flowchart illustrating the step-by-step calculation for sizing a step-up transformer from an inverter's AC rating, starting from 4.0 MW to a final 5.0 MVA standard transformer rating.

Rule 1 — size on AC output at site ambient. Take the inverter’s maximum continuous AC output, not the DC array. A 1.3 DC/AC ratio is normal and does not change the transformer rating; the inverter clips, and the transformer only ever sees the clipped output.

Rule 2 — allow for the inverter’s overload envelope. Many PV inverters deliver 1.05–1.1 p.u. at low ambient temperature. If the site has cold mornings and high irradiance, the transformer should be rated for that, not for the datasheet nominal.

Rule 3 — derate for the real environment. Above 40 °C ambient, above 1,000 m altitude, or inside an enclosure, oil-immersed ratings fall quickly. ONAN to ONAF conversion can recover capacity, but it adds fans, aux power, and a failure mode.

Rule 4 — do not forget station service. Cooling, controls, container HVAC, and BESS thermal management all need an auxiliary supply. A small LV auxiliary transformer is a line item that gets missed in early BOMs and added later at a premium.

Worked example: 100 MW PV plant

  • 25 blocks × 4 MW inverter, 0.69 kV output
  • Transformer per block: 0 MVA, 0.69/33 kV, ONAN (4.4 MVA at 1.10 overload, 4.7 MVA after 45 °C derating)
  • 5 blocks per feeder: 20 MVA, feeder current 350 Aat 33 kV
  • Collector total: 100 MW, 1,750 Aat 33 kV → 2,000 A busbar and incomer
  • Switchgear rating: 25 kA / 3 s, 36 kV, lightning impulse 170 kV

Now the part that surprises people. At the collector, the fault current is dominated by the grid, not by the plant. Each inverter contributes roughly 1.1–1.5 times its rated current, rarely more than 2. Twenty-five 4 MW blocks therefore add only about 2.3 kA at 33 kV, and they add it with a rising, controlled waveform rather than the decaying DC offset of a synchronous machine.

Bar chart showing short-circuit fault current contributions at a 33 kV collector from the grid, synchronous plant, and 25 PV blocks, highlighting the challenge for protection relays.

That number does not size the switchgear — the grid does — but it completely changes how the protection must be set. More on that in section 5.

3. Dry-type or oil-immersed in a PV/BESS plant

The technical comparison is covered in detail in our dry-type vs oil-immersed guide, so here is only the project-level decision.

Utility-scale PV almost always uses oil-immersed transformers in pad-mounted or skid-mounted compact substations. Cost per MVA is lower, overload capability is better, and the equipment sits outdoors where oil containment and fire separation are manageable.

C&I rooftop and building-integrated PV uses cast-resin dry-type, because the transformer sits inside or on a building where an oil fire is unacceptable and spill containment is impractical.

BESS is decided by the fire strategy, not by electrical criteria. If the transformer is inside or adjacent to a container, dry-type removes the oil load from the fire scenario. If it is oil-immersed, separation distances and blast walls usually follow the fire code rather than the electrical design, and NFPA 855 or the local equivalent will drive the layout.

The cost difference is real but rarely decisive: on a 100 MW plant, the transformer choice moves CAPEX by a few percent while the civil and fire-protection consequences can move it by much more.

4. RMU or switchgear? Where each one belongs

This is the configuration question we get asked most often, and the answer is almost always “both, in different places”.

At the block you need three functions: isolate the transformer, earth it safely, and clear a transformer fault. An RMU does all three in 2–4 ways, at 630 A, in a sealed enclosure that needs no maintenance. Add a compact substation enclosure and the transformer, RMU, and LV panel arrive factory-assembled and factory-tested.

At the collector busbar you need current ratings from 1,250 to 2,500 A, busbar sectionalizing, CTs and VTs for metering and protection, and space for relays and communication equipment. That is metal-clad switchgear, with withdrawable circuit breakers so a faulted feeder can be isolated without de-energizing the busbar.

Criterion RMU Metal-clad switchgear
Typical position Block / transformer Collector busbar, incomer, feeder
Rated current 630 A 1,250–2,500 A
Short-circuit 20–25 kA / 3 s 25–40 kA / 3 s
Switching device Load-break switch + fuse, or vacuum CB Withdrawable vacuum CB
Protection Fuse or simple relay Full relay set, CT/VT, metering
Footprint ~1–2 m² 0.6–1.0 m per panel, plus operating corridor
Maintenance Sealed, maintenance-free Periodic, withdrawable
Cost per way Low 4–10× RMU

 

Ring or radial? PV collectors are usually radial, because a ring doubles the cable and the additional availability rarely pays back on a plant that is already curtailed by the grid. BESS, and plants with contractual availability penalties, more often justify a ring: the cost of one extra cable section is small against the revenue lost from an outage.

Diagram comparing radial and ring collector topologies in a PV plant, illustrating the trade-off between cable cost and N-1 redundancy.

SF6-free. Sealed RMUs were traditionally SF6-filled. Vacuum interruption with solid epoxy insulation, or dry-air insulation, now covers the same ratings. The EU’s F-gas Regulation (EU) 2024/573 phases SF6 out of new medium-voltage switchgear, with the first milestone applying to the ≤24 kV class from the start of 2026, and other markets are following with their own rules. For export projects, ask for the SF6-free option at the enquiry stage; retrofitting later is not possible.

5. Protection and metering: the part the utility rejects

This is where PV and BESS projects lose weeks. The grid code at the point of connection is the governing document, and it differs by country: ENTSO-E’s NC RfG in Europe, IEEE 1547 in the United States, and national codes elsewhere. What follows is the engineering logic that sits underneath those codes.

Function ANSI PV BESS Note
Over/under voltage 27/59 Yes Yes Ride-through curves per grid code
Over/under frequency 81U/O Yes Yes  
Rate of change of frequency 81R Yes Yes RoCoF settings are strictest in weak grids
Directional overcurrent 67 Optional Required BESS charges as well as discharges
Non-directional overcurrent 50/51 Yes Yes Must be sensitive to low fault current
Earth fault 50N/51N Yes Yes Sensitive core-balance CT often needed
Anti-islanding — Required Required Active or passive per code
Power factor / Q control — Yes Yes Q(U), fixed PF, or setpoint
Active power control — Yes Yes Ramp rate, frequency response

 

Three engineering points that decide whether commissioning passes:

Fault current is low and controlled. An inverter current-limits at roughly 1.1–1.5 p.u. A 51 curve set for a 5 p.u. fault will simply not pick up. Either set the overcurrent elements very sensitively, add undervoltage-based tripping, or use a communication-assisted scheme such as line differential on long feeders. Distance protection is unreliable against inverter sources because the impedance seen by the relay changes with the control strategy.

BESS flows both ways. Directional elements set for a PV plant will trip the plant the first time it charges. Set the forward and reverse zones independently, and check the metering too: a four-quadrant meter is mandatory for settlement.

CTs must be accurate at low multiples. With fault current barely above load current, a 5P20 CT at 20 times rated is the wrong instrument. Specify class 0.2S for metering and 5P or 10P with a low factor for protection, and check the actual accuracy limit factor against the calculated fault level.

6. Prefabricated or conventional construction

A compact or prefabricated substation arrives with the transformer, RMU, LV panel, wiring, and relays already assembled and type-tested. Site work reduces to foundation, cable termination, and commissioning. On utility-scale projects this typically cuts 30–50% of the electrical site labor, and it moves the quality risk into a factory where it can be inspected.

The constraints are physical: transport envelope, crane access, road width, and lead time. A 40-foot container is the practical limit for road transport in most markets, which caps the transformer size that can ship assembled. Above roughly 5 MVA per unit, conventional construction usually wins on logistics alone.

For BESS, the pattern is a containerized DC block plus an MV skid carrying the transformer and switchgear. The skid is where the interface risk lives: DC and MV are built by different suppliers, and the protection interface between PCS and MV relay is the most common source of commissioning delay.

7. Specification checklist

What to put in the datasheet, in the order a supplier will ask for it:

Item What to state
System voltage / BIL 36 kV / 170 kV, or per local standard
Rated current Per feeder and per busbar, calculated not guessed
Short-circuit System fault level at POC, plus duration
Ambient / altitude Max and min, plus solar gain if outdoor
Enclosure IP rating, anti-corrosion class for coastal sites
Standards IEC 62271-200, 62271-100, 60076, 61439 as applicable
SF6 policy SF6-free, with declaration
Protection Relay functions, protocols (IEC 61850, Modbus)
Metering Class 0.2S, four-quadrant, POC and feeder
Testing Type test reports, routine test reports, witnessed FAT
Documentation Single-line diagram, test reports, O&M manual, spare parts list
Warranty / service Response time, spare modules, local support

 

8. Five mistakes that cost schedule

  1. Sizing the transformer on the DC array.Produces a 20–30% oversize, or the opposite when the inverter’s overload envelope is ignored.
  2. Reusing a load-substation protection philosophy.Inverter fault current does not trip curves designed for the grid.
  3. Copying PV settings into a BESS.The first charge cycle trips the directional element.
  4. Forgetting the auxiliary transformer.Cooling and controls have no supply at commissioning.
  5. Ordering RMUs late.They sit on the critical path between civil works and energization, and the lead time is longer than most project schedules assume.

FAQ

Can one transformer serve both PV and BESS?

Yes, in a hybrid plant. Size for the sum of the two AC ratings, specify bidirectional protection, and meter each source separately for settlement.

Which collector voltage should I use?

33 kV or 35 kV is standard for utility-scale plants above roughly 20 MW. 10 kV is used for smaller plants and where the local grid requires it. The choice is usually dictated by the utility, not by economics.

Do I need a ring or is radial enough?

Radial unless availability is contractual. A ring adds one cable section per loop and buys N-1 on the collector, which matters for BESS and for plants with availability penalties.

How much spare capacity should the collector have?

10–20% on the busbar and incomer. It costs little at the switchgear stage and is expensive to add later.

Can a dry-type transformer go inside a BESS container?

It can, and it removes the oil fire load, but the container’s thermal design and the fire code separation distances still govern. Confirm with the fire strategy before fixing the layout.

Build the MV side once, correctly

The MV system is the smallest part of a renewable project by value and the largest by schedule risk. Getting the transformer rating, the RMU/switchgear split, and the protection philosophy right at the specification stage costs nothing. Fixing them after the grid connection study is rejected costs a quarter.

If you are specifying the MV side of a PV, BESS, or hybrid plant, send us the single-line diagram and the grid code reference. Our engineers will return a configuration and a short-circuit check within five working days.

Latest News

Related Products

Scroll to Top

Get a Quote

Contact Form